The NEXTDC power delay at M3 Melbourne cut the Australian data centre operator’s FY2027 earnings outlook and opened an entry point for two strategic investors. Goodman Group and Digital Realty offered to buy up to 9.9% of NEXTDC through an institutional bookbuild worth approximately A$715 million at the offer price. Their A$9.50-per-share offer was 45.5% above NEXTDC’s A$6.53 close on 4 November. The stock rose as much as 45.8% in early trading the next day. NEXTDC’s board described the approach as opportunistic and said it had received no takeover proposal.

Update on 8 November 2026. Goodman and Digital Realty confirmed that their equally owned vehicle had acquired a 9.9% stake at an average price of A$9.22 per share. Both said they had no current intention of making a takeover offer or submitting a control proposal, while reserving the right to do so if circumstances changed.

How the NEXTDC power delay changed the earnings outlook

On 21 October, NEXTDC said Jemena Electricity Networks had suspended parts of the network upgrade needed to increase power supply to the M3 Melbourne data centre following opposition from community members and other stakeholders. NEXTDC now expects the next increase in grid supply in FY2028. The delay pushes back delivery and billing for contracted capacity that depends on the additional power.

NEXTDC cut FY2027 net revenue guidance to A$475–500 million from A$615–640 million and lowered underlying EBITDA guidance to A$245–265 million from A$385–410 million. The revised ranges exclude the affected M3 contracts, which previously accounted for about A$140 million in expected net revenue and about A$140 million in expected underlying EBITDA. The exclusion covers capacity already billing and any potential service credits. NEXTDC said it could not yet reliably estimate what the affected contracts would contribute in FY2027.

The capacity remains contracted, subject to customer rights. Late delivery or insufficient power could trigger service credits and, in some circumstances, termination. NEXTDC is assessing whether force majeure or other contractual relief applies. For investors, those provisions determine how much of the expected revenue may simply arrive later and how much could be lost.

What the delay means for liquidity and debt covenants

NEXTDC reported A$8.675 billion of liquidity at 30 September, comprising A$1.275 billion in cash and A$7.4 billion in undrawn facilities and committed hybrid capital. Its senior debt covenant update showed pro forma interest cover of 5.91 times against a 1.5-times minimum, and gearing of 8.2% against a 60% ceiling. Those figures show substantial headroom at the reporting date. The timing of customer billing still matters for future tests.

The covenant definition can include annualised EBITDA from contracted capacity that has yet to begin billing when billing is expected within 24 months. NEXTDC excluded the affected M3 contracts’ pro forma contracted EBITDA and any associated service credits from its later headroom illustration. The company expects to comply at the 31 December test. For creditors, the issue is whether revised delivery dates change which earnings qualify for the calculation at subsequent tests.

NEXTDC also issued A$1.1 billion of 1.75% subordinated convertible notes in September. The notes mature in 2031, with a holder put in September 2029. Their initial conversion price of A$16.695 was set against a reference share price of A$12.60. The A$9.50 stake offer was below both levels. The conversion price governs the terms on which noteholders can convert into shares, while the put can bring forward a cash repayment if holders exercise it.

Why grid access matters to strategic investors

A customer contract establishes demand for data centre capacity. Billing depends on when the operator can deliver that capacity at the agreed power and service levels. When network works slip, an operator may still face development costs while waiting to bill customers. Service credits can cut margins, and termination rights can reduce the value of the contracted pipeline. The NEXTDC case shows why a grid connection timetable belongs in both the valuation model and the credit analysis.

An operating platform with secured power, permits and customer relationships may appeal to strategic buyers when a development delay weighs on the share price. Goodman and Digital Realty’s minority stake gives them exposure to NEXTDC’s existing assets and to any recovery in the delayed project. The investment’s value will depend in part on when M3 secures additional power and how much contracted revenue survives the delay. For creditors, any later refinancing, asset sale or control proposal would bring a separate set of questions about covenant protection and the assets supporting repayment.

The Perennial view

The 9.9% acquisition establishes what Goodman and Digital Realty were willing to pay for a minority interest after the earnings reset. The next evidence on M3’s value will come from the network works timetable and the terms that govern customer payments during the delay. At NEXTDC’s 20 November annual meeting, Perennial will watch for updates on power delivery, service credits and any effect on property valuations. The December covenant test will show how the revised outlook feeds into lender headroom, while the 2029 convertible-note put remains a date to track for refinancing.

Explore more analysis on infrastructure, credit and private markets at Perennial Markets.

Where Insight Meets Opportunity.

Sources

Financial-information disclaimer: This publication provides general financial information and independent market commentary only. It is not personal financial advice, an offer, solicitation or recommendation. Equities, debt and infrastructure investments involve market, liquidity, construction, regulatory, counterparty, valuation and loss risks. Eligibility and access may be restricted.