AI infrastructure financing is becoming more selective as the sector prepares to borrow more. Reuters reported on 9 November that some banks were reluctant to increase their exposure even when deals included support from major technology companies. The pullback was most pronounced among independent data centre operators and neoclouds, which rent out computing capacity for AI workloads. At the same time, Goldman Sachs Research projects global hyperscaler debt issuance will rise from an estimated US$250 billion in 2026 to US$420 billion in 2027. The terms on which that capital is available will help determine which projects proceed.

Why AI infrastructure financing is becoming more selective

Investment-grade hyperscalers can draw on operating cash flow and established bond markets, though their borrowing costs have also come under pressure. A Bank of America credit analyst told Reuters that spreads on 10-year hyperscaler debt had widened by about 50 basis points in 2026 to date, compared with about 20 basis points for high-quality industrial issuers outside AI. Independent developers can face a more immediate funding constraint because debt service may depend on a single project reaching completion and beginning to bill customers on schedule.

That makes the scope of customer support important. A guarantee may cover specified payments once a facility is operational. Lenders still need to know who funds cost overruns or services debt if construction slips, the grid connection arrives late or the customer can reduce its capacity commitment. Banks may also limit exposure to a single tenant, guarantor or power market even when individual deals meet their underwriting standards.

What recent deals show about access to capital

Reuters reported that Nebius considered a high-yield bond offering and chose against proceeding with it. In October, the company announced a US$3.5 billion senior secured bridge facility from Citi to support its GPU infrastructure buildout and other corporate needs. The facility matures on 16 October 2027. Its margin starts at 2.75 percentage points over Term SOFR and increases by 0.25 percentage points every 90 days up to 3.50 percentage points, subject to other adjustments. The bridge provides funding for the buildout, while the maturity and step-ups put a timetable on securing longer-term capital or repaying the facility.

Other transactions point to different parts of the market. Reuters, citing Bloomberg, reported that ING was seeking bids for roughly US$500 million of data centre loans. Any completed sales could provide evidence of secondary loan prices. Separately, Reuters reported pressure on CoreWeave’s bonds, a signal of how investors were pricing exposure to a highly leveraged borrower. Together, these developments give lenders several ways to assess funding conditions, from the terms of new facilities to prices on existing debt.

What data centre debt issuance says about investor demand

The CRE Finance Council’s updated primer cites Barclays estimates of about US$116 billion in secured project bonds outstanding as of 8 October, alongside US$44.2 billion in asset-backed securities and US$22.4 billion in commercial mortgage-backed securities. Those figures describe the stock of debt. In the primary market, US data centre asset-backed and commercial mortgage-backed issuance reached US$21.9 billion through October, 7% ahead of the comparable 2025 period. Issuance over the latest three months was 20.2% lower year on year, showing that the pace slowed even as the year-to-date total remained higher.

Moody’s Ratings has flagged refinancing pressure for weaker borrowers as loans mature between 2027 and 2029, according to Reuters. It also pointed to overlapping exposures as technology companies, chipmakers and developers invest in, lend to and buy from one another. A lender may count on customer payments, supplier support and sponsor capital from different entities. If those entities depend on the same expansion plans, their ability to provide support could weaken at the same time.

How tighter underwriting changes project finance

Projects with firm power delivery dates, enforceable customer commitments and meaningful sponsor equity are better positioned to attract financing. Projects with less certain cash flows may need lower leverage, more equity upfront, completion guarantees or draw conditions tied to construction milestones. Some borrowers may turn to private credit for greater certainty of execution. For those lenders, the return depends on pricing the risks they are taking and retaining the ability to intervene if the project runs behind schedule.

Collateral needs to be assessed alongside the contracts. GPUs can lose resale value as newer chips become available, and moving them to another facility can require compatible power, cooling and networking. A financing structure that depends on refinancing a bridge shortly after completion is also vulnerable if grid delays or slower utilisation push back cash receipts. Projects can remain commercially viable and still need to be resized if lenders offer less debt than the original plan assumed. Delayed projects can, in turn, push back orders for Asian suppliers of servers, cooling systems and electrical equipment.

The Perennial view

The next test is whether borrowers with less established cash flow can still complete financings at their original leverage targets. Perennial will watch new-issue spreads, sponsor equity requirements and whether guarantees cover delays, cost overruns or early termination. Secondary loan prices and equipment orders can add evidence on whether tighter terms are changing project schedules. The clearest sign of a lasting split would be continued large-scale issuance from hyperscalers alongside independent projects that need more equity or stronger contracts to close.

Explore more analysis on infrastructure financing and private credit at Perennial Markets.

Where Insight Meets Opportunity.

Sources

Financial-information disclaimer. This publication is for general financial information and independent market commentary. It does not constitute personal financial, legal or tax advice, an offer or a recommendation. Private-market and infrastructure investments are illiquid, complex and may result in partial or total loss. Investors should assess suitability, documentation, valuation, leverage, liquidity, counterparty risk and eligibility with qualified advisers.